Approved Is Not Built: Where Data Centers Actually Die
Nobody publishes a clean average delay or cancellation rate, and anyone quoting one is choosing a denominator. The best trackers say a quarter of 2025 capacity slipped, half of contested projects now die, and about a third of announced U.S. capacity looks buildable. Here is the kill map, gate by gate.
Update, Nov. 18, 2026: Loudoun County’s Board of Supervisors approved the 12-month pause on Nov. 17 by a 7-1-1 vote, with Supervisor Umstattd opposed and Supervisor Kershner abstaining (Loudoun Now, Bisnow). It covers legislative data center and substation applications, with specialized tax districts such as the Rt. 28 Tax District excepted. The references below to the vote as upcoming were written before the result.
In July 2025, the board of Augusta Township, Michigan, voted 7-0 to rezone more than 500 acres of farmland for a hyperscale data center. On August 4, 2026, township voters threw the rezoning out in a referendum, 89.5% to 10.4%. The developer has to find another site, and all seven elected officials now face a recall effort (MLive).
In Virginia, the Prince William Digital Gateway won its rezonings in December 2023 after a 29-hour public hearing. It was planned as 23 million square feet on 2,100 acres. A judge voided the approvals because the county botched a newspaper notice, the Court of Appeals agreed, and on July 2, 2026, QTS withdrew its last appeal and terminated the project (Virginia Business).
Both projects were approved. Neither is going ahead. This piece measures that gap: how long projects slip, how many die, and what kills them after everyone thought the hard part was done.
The two numbers everyone wants
Start with the honest answer. There is no clean, industry-wide average delay for data centers, and no clean cancellation rate. Nobody tracks every project from press release to energization against a fixed original date. Anyone who quotes you a single number has picked a denominator, and the denominator decides the answer.
These are the best proxies we can source.
Delays. Sightline Climate, which now publishes as Currence, tracks projects over 50 MW announced since 2024 and holds each one to the online date it first announced. On that basis, 26% of the capacity expected in 2025 slipped, and another 10% of projects quietly pushed back their operation dates. About 16 GW was slated for 2026, but only about 5 GW was under construction in February, so Sightline expected 30% to 50% of it to be late (Sightline/Currence, methodology). JPMorgan found that 60% of the capacity slated for 2027 had not started construction as of early June (Heatmap).
On the build side, 83% of vendors, designers and consultants in Uptime Institute’s 2026 survey reported supply chain disruption on data center projects, up from 77%. Fifty-eight percent of vendors reported delays of at least three months (Uptime). On the grid side, Wood Mackenzie puts the wait for a new connection at 54 months at best in Virginia and 84 months in Ohio (Wood Mackenzie).
So the delay depends on the gate. A finished hall waiting on one late breaker slips by months. A site still waiting on the grid slips by years.
Cancellations. The numbers run from “almost none” to “most of them,” and each is right about something:
- Sightline counted only nine outright cancellations in February. Delays, not deaths, were the norm (Axios).
- Bernstein, using Aterio data, counted a record 51.7 GW of delayed, cancelled or not-approved capacity in September, 11% of a 456 GW pipeline (Bernstein via TechFlow). It separately estimates only about 35% of announced U.S. capacity, roughly 170 GW, is likely to get built (Business Insider).
- Currence’s Q3 outlook says 55% of the announced 2026 to 2030 pipeline is unlikely to come online (Currence).
- Heatmap Pro says about half of the projects that met local backlash this year were cancelled, up from roughly 40% over five years. Michigan runs at 71%, Indiana 56% and Texas 17%. Heatmap counts at least $260 billion of investment cancelled after local opposition in 2026, about half of it in the third quarter (Heatmap, Oct 6, Heatmap, Jul 30).
The utility funnels are harsher. AEP Ohio had about 30,000 MW of data center requests before its tariff. Only 13,022.7 MW paid for a study, and 5,642 MW signed binding contracts once collateral was due, about 19% of what was asked for (AEP Ohio). ERCOT was tracking more than 438,000 MW of large-load requests in June (Sheppard). It has approved 9,456 MW to energize, and the peak it observed from those loads in September was 4,132 MW (ERCOT). In Georgia, commission staff testified a year ago that 24% of the data center projects entering Georgia Power’s pipeline had been removed (Utility Dive).
Why they disagree. They count different gates. Formal cancellations are rare because projects seldom announce a death. They go quiet, withdraw a rezoning or let an option lapse. Heatmap’s 50% covers only contested projects, so it gives the odds once a fight starts. Bernstein’s 35% runs across everything announced, including landowners testing the market. Utility funnels count requests, and developers file the same project in several territories to see which answers first. Aterio’s tracking shows 30 to 40 GW announced in a typical month, about 7 GW starting construction and 2 to 3 GW starting operation (Business Insider).
The best rule of thumb we found came from Jeffrey Moerdler, a data center lawyer interviewed by Bernstein. Of projects that haven’t started construction, he estimates about a third arrive on schedule, a third are delayed and the rest don’t happen (same source).
For a long-run base rate, look at the power plants these campuses depend on. Lawrence Berkeley National Laboratory found that just 13% of the generating capacity that requested interconnection from 2000 to 2019 was operating by the end of 2024. The typical project built in 2024 took 55 months from request to operation (LBNL). That data covers generators, not data centers, but gas plants now sit on the critical path of many campuses.
The kill list
Power and interconnection. The grid wall gets higher once money is required. AEP Ohio’s letter of agreement makes a customer reimburse 100% of buildout costs if it cancels, or delays more than 12 months, before energization. Customers without strong credit post collateral equal to 50% of minimum charges for the full term, and minimum demand can reach 85% of contract capacity (AEP Ohio tariff). In Texas, most studied load took the “firm” lane, which comes capped at a number nobody has seen yet (our Batch Zero read). Microsoft pulled out of a planned Nscale site in England after grid power for it was pushed into the 2030s (TechCrunch).
Long-lead equipment. Wood Mackenzie puts heavy-frame gas turbines at 278 weeks, roughly early 2032 delivery, with transformers at 162 weeks and circuit breakers at 137 (Wood Mackenzie). Equipment rarely kills a project directly. It pushes delivery past the tenant’s date, and then the tenant leaves. On its November 5 call, IREN said $4 billion of run-rate revenue targeted for year-end now targets January, and could run to the end of February if suppliers are late, “as suppliers have been across the industry this year” (DCD). More in The Backlog Is the Schedule.
Moratoriums, referendums and recalls. Heatmap counts more than 830 restrictive local measures passed this year (Heatmap), and Wood Mackenzie says one-fifth of projects under development have been delayed by a moratorium (Wood Mackenzie). Loudoun County’s board voted November 17 (approved 7-1-1) on a 12-month pause on final votes for data center and substation rezonings and special exceptions, retroactive to September 15 (Virginia Pulse). On November 3, voters sided against data centers in 40 of 41 local ballot measures, by one strategist’s count (Heatmap).
Lawsuits. Prince William died on a newspaper notice. A procedural slip in 2023 killed the project in 2026. The same exposure can sit inside any approval you rely on.
Air permits for on-site gas. On-site power was supposed to be the way around the grid. It now carries its own permit risk. After Gov. Abbott’s September 21 directive, the Texas Commission on Environmental Quality paused every permit for infrastructure directly supporting data centers and is suspending some claimed authorizations where it can (TCEQ). In Mississippi, a federal judge ruled October 30 that the trailer-mounted turbines powering SpaceXAI’s Southaven site are not mobile sources and need permits. The NAACP wants them stopped, and residents are appealing the permit for 41 permanent turbines (Mississippi Today).
Water. Water usually reshapes a project before it kills one. The Western Virginia Water Authority says it will not supply 10 to 11 million gallons a day to Google’s planned Botetourt County campus. The agreement commits 2 million (Roanoke Times). In King George County, Amazon is withdrawing a groundwater permit renewal after a state report warned the Potomac aquifer is declining (Virginia Mercury).
Tax incentive repeal. Between May and August, five states paused data center sales tax exemptions or programs, and Maine, Minnesota and Nebraska repealed theirs. Even failed bills slow things down: in Georgia, builders for two hyperscalers were “dragging their feet” while repeal bills were pending (S&P Global). Yesterday, Texas Senate Finance Chair Joan Huffman, a Republican, filed SB 293 with a majority of senators as joint authors. It would repeal the state’s exemptions and deny applications still pending on its effective date. The Comptroller puts the forgone revenue at about $3.3 billion for the coming biennium (Texas Senate).
State large-load tariffs. Delaware now puts large users in a separate rate class, makes them pay for their own infrastructure and requires them to bring their own generation (S&P Global). Dominion’s GS-5 class starts January 1 (Who Pays for the Large Load?). These tariffs ban nothing. They make speculative projects pay to hold their place, and most drop out.
Tenant pullbacks. In March, Oracle and OpenAI dropped a 600 MW expansion at Abilene after financing talks failed. The Information reported power for it was about a year out, by which point Nvidia’s next generation would be shipping (Tom’s Hardware). In 2025, TD Cowen reported Microsoft had walked away from more than 2 GW in six months (Reuters). A Bernstein analyst and Aterio’s CEO estimate the top players commit to at most about double the capacity they need, as a backup plan (Business Insider). When a hyperscaler walks, it is often an option expiring, not a crisis.
Neocloud credit. CoreWeave’s 2032 bond yields more than 16%, and its five-year default swaps spiked above 1,289 basis points last week (CNBC). Nscale’s IPO filing says it had no binding commitments yet for the financing needed to perform its $44.6 billion Anthropic contract, and Anthropic can end a delivery tranche without liability if Nscale is late (CTOL, citing the S-1). That contract covers a first 460 MW building in West Virginia, and Nvidia is reportedly weighing a guarantee to get it financed (TechCrunch). IREN put it plainly: “the questions have undoubtedly moved from how big the contract is to whether it can be delivered, financed, and run at a profit” (DCD).
Labor. In the AGC and NCCER 2026 survey, worker shortages were the most common reason for project delays, cited by 42% of respondents. Only 26% reported no significant delays (AGC).
Design changes. Chips change faster than buildings get built. IREN handed Microsoft a finished hall, then Microsoft asked for network changes to serve the latest frontier models, which added to the delay (DCD). At Abilene, a winter outage that hit liquid cooling equipment was among the problems reported around the expansion decision (Tom’s Hardware).
The stage-gate kill map
This is our synthesis of the sources above. The mortality column is our judgment, not a measured rate.
| Gate | What kills here | Mortality (our read) | Ask before you count it |
|---|---|---|---|
| Announced | No power path, no tenant, same project filed in several places | Highest | What has this developer actually delivered? |
| Land | Options lapse, seller walks, title or easement problems | High | Owned or optioned? When does the option expire? |
| Zoning | Moratoriums, denials, referendums, notice defects | High, and rising | Past the referendum and appeal windows? Was notice done by the book? |
| Power study | Study runs past the tenant’s date or comes back too small | High | How many MW by year, and how much of it is firm? |
| Power agreement | Collateral, minimum bills, exit fees, capped firm service | Medium to high | Signed, collateral posted? What does a 12-month delay cost? |
| Permits | Air permits for on-site gas, water supply, state pauses | Medium | Which permits are final, and which are only pending? |
| Financed | Credit spreads, unclosed financing, tenant walk rights | Medium | Debt closed or term sheet? What triggers termination? |
| Under construction | Equipment slots, labor, design changes | Low for deaths, high for delays | Transformers, switchgear and turbines on order, with slot dates? |
| Energized | Ramp schedules, curtailment terms | Low | MW billing today against MW contracted? |
The pattern is consistent. Most projects die before construction. Bernstein analyst Madison Rezaei expects most speculative projects to fail before they borrow serious money through project finance, which is why Bernstein doesn’t expect a wave of unpaid debt (Business Insider). Heatmap says most cancellations come from a failed local permit or a hostile local government action. Once concrete is poured, a project is far more likely to be late than dead.
What is actually happening
Three things changed in 2026.
“Approved” stopped being a safe word. A rezoning used to be the point where a project counted as real. This year voters reversed approvals by referendum, courts voided them years later, and state agencies froze permits for projects that already had zoning. The risk now runs past the approval date, and most underwriting hasn’t caught up.
Utilities are running the filter. AEP Ohio cut 30 GW of requests to 5.6 GW of signed load with paperwork and collateral. It didn’t need a ban. Every new large-load tariff turns a pipeline headline into a much smaller contracted number. That is good for the grid and bad for any deck built on requested megawatts.
Lenders are pricing delay. Tenants hold walk rights tied to delivery dates, and neocloud bonds trade like the market doubts delivery. A six-month slip used to be an annoyance. Under a termination clause, it can end the deal.
What to ask, by seat
Buyers and tenants: ask for documents at each gate. That means the signed electric service agreement, the collateral posted and the delay penalty, not a “power secured” slide.
Developers: price the late gates into the schedule. An approval with a notice defect, or a plan that needs gas permits in a state that just paused them, is not a finished entitlement. Order long-lead gear against signed power.
Investors and lenders: haircut announced megawatts by gate. Bernstein’s credible share is about 35% market-wide and nearly 80% for capacity the largest tech companies develop directly (Business Insider). Read the tenant’s termination triggers before the headline contract value. Not investment advice.
Read the signed column, not the pipeline
The pipeline is a list of options. The signed column is the projects with a power contract, collateral posted, final permits, closed debt and a tenant without an easy exit. In AEP Ohio’s numbers that is 5,642 MW out of 30,000 requested. In ERCOT’s it is 9,456 MW approved and 4,132 MW observed running. We called this the gap between announced and spoken-for in Contracted Megawatts Are the Ones That Count. In 2026, voters, courts, state agencies and lenders all made it wider.
What to watch:
- November 17: Loudoun approved the 12-month pause, 7-1-1.
- By December 10: ERCOT’s Batch Zero verification report to the PUCT.
- January 2027: Virginia’s General Assembly takes up moratorium bills, including SB 843, which would bar approvals statewide from July 2027 to July 2030 (Virginia Pulse), and Texas convenes with SB 293 on file.
- Southaven: the ruling on the NAACP’s request to stop the unpermitted turbines, and the residents’ permit appeal.
- Neocloud financing: whether Nvidia’s guarantee for Nscale closes, and where CoreWeave’s spreads go after earnings.
Counts and rates come from the trackers and filings linked above, and they measure different things, as explained. The stage-gate mortality ratings are our editorial judgment. This post is for information only and is not legal, engineering or investment advice.
Sources
- https://www.currence.ai/blog/data-center-outlook ↗
- https://www.axios.com/2026/02/24/ai-data-center-boom-projects-numbers ↗
- https://www.currence.ai/blog/currence-data-center-delays ↗
- https://www.currence.ai/blog/q3-2026-data-center-outlook ↗
- https://heatmap.news/daily/260-billion-data-center-opposition ↗
- https://heatmap.news/politics/data-center-local-laws-bans-total ↗
- https://heatmap.news/politics/data-center-restrictions-midterms ↗
- https://www.datacenterwatch.org/q2-2026 ↗
- https://www.bisnow.com/news/national/data-center-community-relations/community-backlash-upends-billions-of-dollars-in-new-data-center-projects ↗
- https://www.techflowpost.com/en-US/article/34522 ↗
- https://www.businessinsider.com/ai-data-centers-never-built-bragawatts-kevin-oleary-2026-10 ↗
- https://www.woodmac.com/blogs/the-edge/speed-to-power-solutions-us-data-centres-challenges/ ↗
- https://eta-publications.lbl.gov/sites/default/files/2025-12/queued_up_2025_edition_12.15.2025.pdf ↗
- https://datacenter.uptimeinstitute.com/rs/711-RIA-145/images/2026.AnnualSurvey.SupplierViewReport.pdf ↗
- https://www.aepohio.com/company/news/view?releaseID=10753 ↗
- https://www.aepohio.com/company/about/rates/data-center-tariff/ ↗
- https://www.ercot.com/files/docs/2026/10/16/ERCOT-Monthly-Operational-Overview-September.pdf ↗
- https://www.sheppard.com/insights/blogs/puct-approves-batch-zero-framework-that-will-provide-a-pathway-for-large-load-to-connect-to-the-grid-and-receive-electricity ↗
- https://www.utilitydive.com/news/georgia-power-large-load-data-centers/806300/ ↗
- https://www.mlive.com/news/ann-arbor/2026/08/voters-in-augusta-township-reject-rezoning-farmland-eyed-by-data-center-project.html ↗
- https://virginiabusiness.com/prince-william-digital-gateway-data-center-project-officially-dies/ ↗
- https://mississippitoday.org/2026/11/02/federal-judge-southaven-data-center-gas-turbines-must-have-air-permits/ ↗
- https://www.tceq.texas.gov/downloads/response/tceq-response-gov-abbott-dc-directive.pdf ↗
- https://roanoke.com/news/local/business/development/article_22c4989d-36f1-430d-9ece-b42bca55ca52.html ↗
- https://virginiamercury.com/2026/08/26/amazon-changes-course-on-water-use-for-king-george-data-center-campus/ ↗
- https://www.spglobal.com/energy/en/news-research/latest-news/electric-power/091126-where-states-stand-on-data-center-sales-tax-exemptions-ahead-of-us-midterms ↗
- https://senate.texas.gov/members/d17/press/en/p20261109a.pdf ↗
- https://www.tomshardware.com/tech-industry/oracle-and-openai-scrap-planned-600mw-abilene-expansion ↗
- https://www.reuters.com/technology/microsoft-pulls-back-more-data-center-leases-us-europe-analysts-say-2025-03-26/ ↗
- https://www.datacenterdynamics.com/en/news/microsoft-design-change-delays-irens-data-center-delivery-in-texas/ ↗
- https://www.cnbc.com/2026/11/06/coreweave-bond-yield-tops-16percent-as-ai-credit-stress-rises.html ↗
- https://www.ctol.digital/news/nscale-anthropic-contract-nvidia-guarantee/ ↗
- https://techcrunch.com/2026/10/30/nvidia-weighs-playing-the-cosigner-for-nscales-ai-data-center-in-west-virginia/ ↗
- https://www.agc.org/sites/default/files/users/user21902/2026%20Workforce%20Survey%20Analysis%20%284%29.pdf ↗
- https://www.thevirginiapulse.com/stories/loudoun-data-center-pause-deferred ↗