INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST
Markets / N. Virginia
C&W 2026 Americas · Primary #3 · updated 2026-11-05

Virginia: Northern Virginia + Richmond

The biggest market is the most constrained. Only 10.8 MW is available, Loudoun has frozen applications for 12 months, there is a new per-kWh tax, and Dominion's wait runs multiple years. Existing grandfathered and powered positions just became scarcer and more valuable. New greenfield entitlements are effectively paused in Loudoun.

coolingGrid: Dominion Energy (PJM); NOVEC; Rappahannock Electric

CBRE H1 2026: largest North American market by inventory (4,496.5 MW) [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05); CBRE, North America Data Center Trends H1 2026 (2026-08)]

Power and the queue

Notable projects owners where public

Regulatory posture incentives, moratoria, zoning, water, large-load rules

Pending legislation and actions 4 items

DateJurisdictionItemStatusImpactSource
2026-02-06Virginia
state
HB1515 (2026)
Proposed a temporary local approval moratorium until the earlier of fulfillment of pending data center interconnection requests or 2028-07-01.
pendingmedium[LIS Legislation Event History API - HB1515 (2026, LegislationID 101057)]
2026-02-12Virginia
state
HB503 (2026)
Would prevent utility costs substantially related to serving data center customers of 100 MW or more from being recovered from non-data-center customers unless rates substantially recover those costs from data centers.
pendinglow[LIS Legislation Event History API - HB503 (2026, LegislationID 99308)]
2026-02-12Virginia
state
SB466 (2026)
Would prohibit recovery from other customers of distribution infrastructure costs primarily serving data centers.
pendinglow[LIS Legislation Event History API - SB466 (2026, LegislationID 100440)]
2026-02-11Virginia
state
HB641 (2026)
Proposed a Virginia's Great Outdoors Act and a data center land conservation tax of $3 per square foot of data center facility footprint.
pendinglow[LIS Legislation Event History API - HB641 (2026, LegislationID 99453)]

In force / enacted 14 items

DateJurisdictionItemStatusImpactSource
2027-01-01Dominion Energy Virginia
utility
GS-5 large-load rate classuncertain
A separate class effective Jan 1, 2027, with 14-year service commitments and minimum charges.
enactedhigh[Dominion Energy: GS-5 Large Load Rate Class report (2026-11-05)]
2026-10-09PJM (13 states + DC)
utility
FERC order ER26-3515: PJM Large Load definition and registry
FERC accepted the definition and registry, effective Oct 12, 2026, and rejected the rest of the filing. The registry is not a public per-request queue.
enactedhigh[FERC order ER26-3515 on PJM Large Load definition and registry (2026-10-09)]
2026-09-16Loudoun County
county
12-month pause on new data center applicationsuncertain
The Board voted 7-1 for a pause effective immediately, to revise regulations. A formal resolution was due Oct 20.
in forcehigh[DCD: Virginia's Loudoun County board votes to pause new data center applications (2026-09-18)]
2026-08-05Prince William County
county
PW Digital Gateway rezonings voideduncertain
The rezoning approvals are void and the parcels reverted to prior zoning. Any new rezoning has to start over.
in forcehigh[Prince William County: PW Digital Gateway status page (2026-11-05)]
2026-07-28Montgomery County
county
Expedited Bill 19-26 (Department of Permitting Services barred from issuing data center permits during the moratorium) paired with Zoning Text Amendment 26-01 (prohibits hyperscale data centers county
Council intends to use the 18-month period to develop comprehensive data-center development guidelines in coordination with state officials. Duration: 18 months from the bill's effective date (specific calendar end date not stated in the press release)
in forcehigh[Council Approves 18-Month Data Center Moratorium and Places Limitations on Data Center Dev]
2026-07-06Front Royal
town
Resolution Establishing a Temporary Ninety (90) Day Moratorium on the Acceptance of Data Center Land Use Applications, adopted 6-0 by Front Royal Town Council at its July 6, 2026 work session. Town At
Front Royal Town Council adopted a 90-day administrative moratorium on data center land-use applications while it drafts a permanent zoning prohibition. Duration: 90 days from adoption (to approximately 2026-10-04).
in forcehigh[https://www.frontroyalva.com/AgendaCenter/ViewFile/Minutes/_07062026-1476]
2026-07-01Frederick County
county
Executive Order No. 05-2026 (effective 2026-09-14, signed by County Executive Jessica Fitzwater), which supersedes and extends Executive Order 04-2026 (effective 2026-07-01, following the Maryland Sup
Pause intended to allow community engagement and to await the State's forthcoming data-center impact report before further zoning action. Duration: Through 2027-07-01 (or until superseded/terminated earlier), per Executive Order No. 05-2026, effective 2026-09-
in forcehigh[County Executive Rejects Community Benefits Agreement (2026-09-14)]
2026-06-29Virginia
state
2026-28 budget, HB30 Item 3-5.24: data center electricity consumption tax
Temporary $0.011/kWh tax on data center electricity, including self-supply, from Jul 1, 2026 to Jun 30, 2028, capped at $600M a year with pro-rata refunds. The sales-tax exemption was kept.
enactedhigh[Virginia budget HB30 (reenrolled) Item 3-5.24: Data center electricity consumption tax (2026-06-29)]
2026-06-01Howard County
county
CB31-2026 (the S.M.A.R.T. Siting Act)
County Council passed CB31-2026 as amended on 2026-06-01; County Executive Calvin Ball signed it 2026-06-04; it took effect 2026-08-04 and, unless superseded by earlier zoning legislation, remains in force through 2027-11-02. Duration: Ends at the earliest spe
in forcehigh[Queen Anne's County joins 5 other Maryland counties fighting against data center developme (2026-06-04)]
2025-09-16Prince George's County
county
CR-098-2025; Executive Order 1-2026; underlying task force created by CR-016-2025
As of 2026-07-31, no comprehensive data-center zoning ordinance has been enacted. Instead, the Council extended the temporary pause via CR-066-2026 (2026-07-07, two years). A competing zoning proposal by Councilmember Wanika Fisher to permit data centers in sp
in forcehigh[Prince George's County Council - Reference No. CR-066-2026 (2026-07-07)]
2026-04-13Virginia
state
HB153 (2026)
Adds Va. Code section 15.2-2209.4. Requires localities to obtain a sound-profile site assessment for new high energy use facilities of 100 MW or more near homes or schools within 500 feet; allows optional review of water, agriculture, parks, historic sites, an
enactedmedium[LIS Legislation Event History API - HB153 (2026, LegislationID 98797)]
2026-04-13Virginia
state
HB496 (2026)
Requires registered water users that provide offsite water to report potable and reclaimed water volumes supplied to data centers with DEQ air permits, along with other use categories where available.
enactedmedium[LIS Legislation Event History API - HB496 (2026, LegislationID 99301)]
2026-04-13Virginia
state
SB94 (2026)
Companion / identical enacted high energy use facility site-assessment bill; incorporated SB130.
enactedmedium[LIS Legislation Event History API - SB94 (2026, LegislationID 98848)]
2024-09-10Fairfax County
county
Data center zoning ordinance amendment
200-ft residential setbacks, generator distance rules and noise studies.
in forcemedium[Fairfax County: Board approves data center zoning ordinance amendment (2024-09-11)]

Open the full VA tracker →

Pricing & supply snapshot directional

MW Desk estimate / directional range, Q4 2026

Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.

  • Retail colo (roughly 0–250 kW): $150–355/kW-mo
  • Wholesale (roughly 250 kW–4 MW): $100–270/kW-mo
  • Large / hyperscale blocks (roughly 4 MW+): $105–220/kW-mo
  • Vacancy band: under 0.5% (extremely tight)
  • Commissioned inventory (directional): ~6.5–7.2 GW
  • Available power (directional): ~15–40 MW
  • Under construction: ~430–520 MW
  • Planned pipeline: ~12.5–13.0 GW
  • Absorption: solid positive absorption
  • Power / timing: Immediate powered shell is scarce; expect multi-year waits for net-new large-load service in constrained pockets.

Blends Northern Virginia with Richmond; NOVA dominates inventory and vacancy.

Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.