INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST
Markets / DFW
C&W 2026 Americas · Primary #1 · updated 2026-11-05

Dallas-Fort Worth

This is the #1-ranked market, but new 75 MW+ loads are frozen at the grid level and a new governor wants a statutory moratorium. Existing energized and pre-audited capacity is gold. Underwrite new DFW load assuming a 2027-or-later energization at best.

mixedGrid: Oncor and other ERCOT TDSPs (ERCOT)

C&W ranked Dallas the #1 primary market globally for the first time [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05); DCD: Global data center capacity under construction reached 31.7GW in 2025 (C&W report) (2026-05)]

Power and the queue

Notable projects owners where public

Regulatory posture incentives, moratoria, zoning, water, large-load rules

Pending legislation and actions 3 items

DateJurisdictionItemStatusImpactSource
2026-11-10Fort Worth
city
90-day moratorium process + closed-loop cooling rule
Closed-loop cooling is required for new data centers (adopted Aug 11, 2026). The moratorium hearing is Nov 10, with adoption tentatively Feb 16, 2027.
pendinghigh[City of Fort Worth: Data Centers (moratorium schedule, closed-loop cooling policy) (2026-09-29)]
2026-11-04Texas
state
Governor-elect pledge: statutory moratoriumuncertain
Gina Hinojosa (elected Nov 3) campaigned on an immediate moratorium lasting until the Legislature passes protections. BMI says the pause could plausibly extend into late 2027.
proposedhigh[DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections (2026-11-04)]
undatedDenton
city
Not yet adopted; a proposed ordinance following a two-track process (moratorium plus separate development-code amendments) is pending Council hearings.uncertain
Two-track process pending: a possible temporary (about 3-month) moratorium and separate, permanent development-code amendments; first of two required public hearings held 2026-09-22, second scheduled 2026-10-27, possible final vote as early as 2026-12-02. Dura
pendingmedium[https://www.cbsnews.com/texas/news/denton-data-center-moratorium-public-hearing-september-]

In force / enacted 4 items

DateJurisdictionItemStatusImpactSource
2026-09-21Texas
state
Governor directive: TCEQ to halt data center permits
TCEQ is to issue no permits for infrastructure directly supporting data centers until ERCOT's audit is complete. TCEQ reported compliance on Oct 19, and a watchdog says some permits still advanced.
in forcehigh[Office of the Texas Governor: Governor Abbott directs TCEQ to halt data center permits (2026-09-21)]
2026-08-07Lavon
city
City of Lavon moratorium ordinance on data center projects
City studying zoning/infrastructure impacts before allowing new data center applications Duration: 90 days, extendable for another 90 days
in forcehigh[https://www.yahoo.com/news/us/articles/lavon-approves-90-day-moratorium-020542449.html]
2026-08-03Texas
state
Governor directive: comprehensive data center audit (ERCOT Batch Zero)
PUCT/ERCOT must verify and audit data centers in the interconnection queue. ERCOT is not approving energization of new data center and crypto loads of 75 MW or more until the audit is complete. Verification and community-impact reports are due Dec 10, 2026.
in forcehigh[Office of the Texas Governor: Governor Abbott directs comprehensive data center audit (2026-08-03)]
2025-06-20Texas
state
SB 6 (89R, 2025)
Requires PUCT/ERCOT large-load planning and interconnection standards; applies to large loads at a default 75 MW single-site threshold; addresses interconnection studies, cost allocation, co-location, and emergency curtailment
enactedhigh[SB 6 (89R, 2025) primary source (2025-06-20)]

Open the full TX tracker →

Pricing & supply snapshot directional

MW Desk estimate / directional range, Q4 2026

Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.

  • Retail colo (roughly 0–250 kW): $140–355/kW-mo
  • Wholesale (roughly 250 kW–4 MW): $100–275/kW-mo
  • Large / hyperscale blocks (roughly 4 MW+): $110–195/kW-mo
  • Vacancy band: under 1% (extremely tight)
  • Commissioned inventory (directional): ~2.4–3.1 GW
  • Available power (directional): ~0–45 MW
  • Under construction: ~30–120 MW
  • Planned pipeline: ~9.8–10.5 GW
  • Absorption: strong positive absorption
  • Power / timing: Immediate powered shell is scarce; expect multi-year waits for net-new large-load service in constrained pockets.

Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.