The Shell Is a Bond Now. The Megawatt Is the Bet.
Blackstone's new data center trust is paying a 7.0% cap rate for 13 finished, leased shells. Days earlier, Fermi lost its only tenant and signed a non-binding LOI for 600 MW of powered land. The risk in this business now sits between those two deals, and Washington just moved to price it.
Update, Nov. 18, 2026: Loudoun County’s Board of Supervisors approved the 12-month pause on Nov. 17 by a 7-1-1 vote, with Supervisor Umstattd opposed and Supervisor Kershner abstaining (Loudoun Now, Bisnow). Specialized tax districts such as the Rt. 28 Tax District are excepted, and substations needed for grid reliability are exempt. The text below was written before the vote.
Two deals from the past week show how the data center market now prices risk.
On Monday, Blackstone Digital Infrastructure Trust ($BXDC) agreed to buy a 75% stake in two joint ventures with a hyperscaler, in a deal valued at about $5 billion at an initial cap rate of 7.0% (Blackstone). The ventures own 13 newly built powered shells on two campuses. The hyperscaler seller keeps 25% and leases back all of it, triple net, for an initial 12 years and up to 32 years with extensions. It is the trust’s first deal and a deployment of its IPO proceeds.
Last Thursday, Fermi ($FRMI) disclosed that its build-to-suit lease with AI cloud TensorWave was terminated on November 10, after the closing date passed without an extension (Fermi 10-Q). The AMD credit support behind that lease is gone too (DCD). The same day the lease died, Fermi signed with an unnamed investment-grade hyperscaler for about 600 MW of powered land at Project Matador in the Texas Panhandle (Baxtel). The press release talks about agreements (Investing.com). The 10-Q calls the core document a non-binding letter of intent, backed by a $200 million prepayment and a $15 million early construction and site development agreement. There is no lease.
Put them side by side and you get the argument of this post. A finished, leased data center now trades like a bond. An unfinished megawatt trades like a venture bet. The spread between the two is where the money and the risk in this business live, and this week’s policy news widened it.
The finished building trades like fixed income
Read the Blackstone release for what it leaves out. There is nothing about GPUs, AI demand or rack density. The pitch is “newly-constructed, income-generating, stabilized” properties “leased to investment-grade hyperscale tenants on long-term contracts,” with “contractual rent escalations.” That is how a net-lease REIT talks about a drugstore portfolio. Here it is applied to the most fought-over real estate in the country.
The seller’s side is the more interesting one. A hyperscaler that builds shells, fills them, then sells 75% to a listed income vehicle is pulling capital out of the part of the business that is finished. It keeps the buildings through the leaseback and a quarter of the equity. It gets cash back for the part that is not finished: power, land and the next campus.
The unfinished megawatt trades like an option
Now look at what the hyperscaler at Fermi is paying for. It is not a building. “Hyperscalers want sites that are ready with permitted power,” Fermi CEO Lee McIntire said (DCD). Fermi says the customer is “making financial and development commitments ahead of finalizing a lease, reflecting the importance of securing access to power within its targeted delivery timeline.” The two sides are also finalizing a $90 million purchase agreement for structural steel and building materials that Fermi bought in advance.
So the buyer is paying cash for a place in line on power and long-lead materials, and leaving the lease decision for later. Fermi’s lenders priced it the same way. Its turbine warehouse financing had a condition tied to signing a lease or offtake for at least 400 MW at Project Matador by November 10. An October amendment removed it. The separate requirement to close project financing for the first phase by February 10, 2027 is still there (Fermi 10-Q).
CoreWeave ($CRWV) showed the same pattern from the tenant side. It reported 1.7 GW of active power against 4.6 GW contracted, and said short-term capacity is pricing at about $40 million per megawatt per year, against $20 million to $25 million for new four to five year contracts (CoreWeave Q3 call). Compute on capacity that is live today rents for roughly double the long-contract rate. That is what a time premium looks like when the bottleneck is the meter.
At DCD’s Virginia event, the talk was of hyperscalers reported to be walking away from leases where timelines slipped too far (DCD). Tenants hold the options. Developers write them.
Washington just priced the gap
The bipartisan permitting bill in the Senate, the Bipartisan American Affordability and Jobs Act, would speed federal reviews for transmission lines and pipelines. It would also make data centers pay more for the grid (NYT via the Inquirer). Section 2107 would have FERC drop its 1994 bar on “and” pricing for transmission serving data centers, so a utility could charge them for both the embedded cost of the existing grid and the incremental cost of serving them (Grid Strategies).
Grid Strategies puts that at $55 billion over ten years. Data centers pay roughly $2 billion a year for transmission now, so the change adds about $35 billion across the decade. If states fully use the bill’s Ratepayer Protection Floor, the firm sizes possible extra generation charges at another $136 billion over ten years, as an indication of magnitude rather than a forecast. The model runs on 40.3 GW of new data center additions and leaves out ERCOT (TechTarget).
That detail matters here. The cost estimate is built on capacity that does not exist yet, which is exactly where the capital is thinnest and the calendar least certain. A stabilized shell on a triple net lease passes operating costs to its tenant by design. A powered-land deal waiting on a lease has no one to pass them to.
Local policy is moving the same way. Loudoun County’s board voted on Nov. 17 (approved 7-1-1, see the update above) on a resolution pausing action on legislative applications for data centers and non-reliability substations for up to 12 months while it finishes its Phase 2 data center standards (Loudoun staff report). Before the vote, staff counted 33 active applications and expected Phase 2 adoption around July 2027. In the biggest market in the world, that holds back new supply and makes every existing powered shell scarcer.
PJM shows the other side of the ledger. Its utilities trimmed near-term large-load forecasts by 6.5 GW, which Jefferies says could shrink PJM’s backstop procurement to as little as about 630 MW from a 6.8 GW target. A Charles River Associates study for PJM still sees a shortfall of roughly 11.5 GW by 2030 (Utility Dive). Speculative load is getting squeezed out, and the real load still lacks supply. Both facts favor whoever is already energized.
Labor and steel sit on the same line
The crews who turn a bet into a bond are scarce too. Roughly 1 in 6 Associated Builders and Contractors members is under contract on a data center, a record. Those contractors carry 9.9 months of backlog, against 8.3 for everyone else, and ABC’s chief economist says labor scarcity “is reemerging as a major headwind” (ABC). The $90 million steel deal at Fermi is the same story from the materials side. The customer wants the long-lead inventory someone else already bought.
The industry is unbundling to match. PowerBridge broke ground on a powered land campus near Pecos, Texas, with 300 MW of first-phase generation and first power expected in Q4 2027. Others will develop the buildings, and no end users have been announced (DCD). Power developer, shell builder, yield buyer, tenant. Each layer now has its own buyer and its own cost of capital.
Builders, buyers, investors
Developers. Your exit price is set by the bond buyer. Your risk is set by the utility, the county and the electrical sub. The step that is gaining value is the conversion from powered land to an energized, leased shell. Underwrite to the date the meter turns on, and get paid for time, not acreage.
Landowners and powered-land sellers. Prepayments and LOIs are real cash. They are not leases. Read the refund and termination terms the way Fermi’s lenders did.
Capital. A 7.0% cap on 12-year triple net hyperscale paper is now a public price point. Everything upstream has to clear it by enough to pay for entitlement risk, a possible new transmission charge and a contractor backlog measured in months. If the spread on offer doesn’t, you are taking bond money for venture risk.
Public-market investors. The tickers in this story sit on different sides of the spread: $BXDC and $BX on the finished side, $FRMI and $CRWV with large unbuilt or not-yet-energized books, $AMZN as a seller of finished shells. Nothing here is a view on any of them. Not investment advice.
What to watch
- Loudoun’s pause, approved Nov. 17, 7-1-1: legislative applications in specialized tax districts such as the Rt. 28 Tax District are excepted, and applications near the 12-month state deadline will be taken up if the applicant refuses to extend.
- BXDC’s closing, expected in the fourth quarter, and whether other hyperscalers start selling stabilized shells into listed or private income vehicles.
- Fermi’s February 10, 2027 deadline to close first-phase project financing, and whether the 600 MW LOI turns into a lease before then.
- The bill’s path through the Senate, and whether the “and” pricing language survives. The Data Center Coalition says it is still reviewing the bill.
- FERC’s large-load dockets. Responses from five grid operators were due November 16, and SPP’s is due November 20 (FERC).
The argument about whether AI demand is real is over. The live question is who carries the years between a signed LOI and an energized lease, and what they get paid for it. This week the market quoted both ends.
Sources
- Blackstone, “Blackstone Digital Infrastructure Trust Announces $5 Billion Acquisition of Stabilized Data Center Portfolio,” Nov 16, 2026: blackstone.com ↗
- Fermi Inc., Form 10-Q for Q3 2026, Subsequent Events note: sec.gov ↗
- DCD, “Fermi agrees 600MW power deal with hyperscaler, but TensorWave lease is officially dead,” Nov 13, 2026: datacenterdynamics.com ↗
- Investing.com, “Fermi secures 600 MW hyperscaler deal, terminates TensorWave lease”: ca.investing.com ↗
- Baxtel, “Fermi Secures 600MW Hyperscaler Deal, Terminates TensorWave Lease”: baxtel.com ↗
- The Motley Fool, “CoreWeave (CRWV) Q3 2026 Earnings Call Transcript,” Nov 10, 2026: fool.com ↗
- DCD, “DCD Connect Virginia 2026: It’s all about the power (and public perception),” Nov 13, 2026: datacenterdynamics.com ↗
- Grid Strategies, “Grid Funding from Data Centers in the Bipartisan American Affordability and Jobs Act (BAAJA),” Nov 2026: gridstrategiesllc.com ↗
- TechTarget, “Data center operators might pay $55 billion under Senate bill,” Nov 2, 2026: techtarget.com ↗
- The Philadelphia Inquirer (New York Times), “Congress looks to charge data centers billions in sweeping energy plan,” Nov 16, 2026: inquirer.com ↗
- Loudoun County Board of Supervisors, Nov 17, 2026 action item, “Resolution to Pause Board of Supervisors Consideration of Legislative Applications for Data Centers and Substations”: pub-loudoun.escribemeetings.com ↗
- Utility Dive, “PJM’s revised data center backstop procurement plan reduces utility risks: ICF,” Nov 3, 2026: utilitydive.com ↗
- Associated Builders and Contractors, “ABC Survey: 1 in 6 Members Perform Data Center Work; Backlog Rebounds in August,” Sept 15, 2026: abc.org ↗
- DCD, “PowerBridge breaks ground on gigawatt-scale powered land campus in Texas,” Nov 13, 2026: datacenterdynamics.com ↗
- FERC, “Cost Transparency and Customer Protection Initiatives in FERC’s June 2026 Show Cause Orders for Large Load Interconnections”: ferc.gov ↗