INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST

THE MW DESK / BLOG

Field notes on power,
permission and delivery.

Source-linked analysis — not a press-release rewrite. Follow @Day2Gigawatt for the short version.

FEATURED
8 minpolicy, power, fuel-cells, capital

Voters Said No. Operators Built Their Own Power Plants.

Data centers were on the ballot in at least 40 jurisdictions. The same week, Google and NTT signed for about 1.6 GW of on-site fuel cells. Siting got harder. Operators are buying down calendar risk.

Read →
8 minrates, utilities, dominion, aps

Who Pays for the Large Load?

Dominion's GS-5 class hits January 1, 2027 with 14-year commitments and minimum charges. APS wants collateral and exit fees. The fight over AI power is becoming a fight over other people's bills.

Read →
9 minpricing, markets, 2027, capital

What Q4 2026 Is Telling You About 2027 Pricing

Record construction, 1.4% vacancy, GS-5 minima, Texas pause risk, 160-week transformers and hyperscaler credit wraps. Directional rents stay firm where power is real. Speculative shells pay in coupon, not in asking rate.

Read →
9 minmarkets, vacancy, capacity, sublease

Vacancy Fell While Construction Broke Records

CBRE: primary-market supply up 33.7% to 10.9 GW, construction at 7,481 MW, vacancy down to 1.4%. Northern Virginia sits at 0.24% vacant with 10.8 MW available. Scarcity is the product.

Read →
7 minlabor, construction, electricians, schedule-risk

The Real Talent War Is for Electricians

AGC's 2026 survey: 28% of contractors worked a data-center job last year, and among them worker availability is the top delivery challenge. Capex announcements do not hire journeymen.

Read →
8 minsupply-chain, transformers, switchgear, eaton

The Backlog Is the Schedule

Caterpillar's backlog hit $78B. Eaton's Electrical backlog is up 46%. Substation transformers sit past 160 weeks. Clearing a grid queue does not clear a factory queue.

Read →
7 minohio, pjm, policy, moratorium

Ohio Voted. The Pipeline Felt It.

At least 14 Ohio communities banned or capped data centers on Election Day. Grove City now requires a public vote above 50 acres, 20 MW or 500,000 gallons a day. Local politics is a site criterion.

Read →
9 minnuclear, smr, microsoft, constellation

Nuclear for Data Centers Runs on Two Clocks

Hyperscalers have signed roughly 8.5 GW from existing and restarting U.S. reactors. Conditional SMR deals top 45 GW. Only one data-center-tied new reactor is under construction. Do not confuse the two clocks.

Read →
8 minnatural-gas, entergy, meta, utilities

Natural Gas Is the Bridge — and the Argument

Entergy plans seven combined-cycle plants totaling 5,278 MW and about $12.9B around Meta's Louisiana campus. APS wants 4,000 MW of gas through 2036. AI load is rewriting utility resource plans in methane.

Read →
8 mininterconnection, caiso, pjm, queues

Flexibility Is the New Interconnection

CAISO will file a plan letting large loads connect before network upgrades finish — if they accept enforceable flexibility. PJM has a Large Load registry without a public queue. The wires are late; the contracts are changing.

Read →
8 mincooling, water, chemours, design

Cooling Without Assuming the River

Google's Wyoming campus will be air-cooled. Chemours launched two-phase fluids that can cut cooling water toward zero. Grove City's ballot trigger includes 500,000 gallons a day. Water is now a siting veto.

Read →
7 minutilities, power, alliant, aps

Contracted Megawatts Are the Ones That Count

Alliant has 3.4 GW of data-center demand under contract and expects another 1 GW in six months. APS is writing collateral and exit fees for loads that never show. Announced MW is not spoken-for MW.

Read →
7 minpower, fuel-cells, behind-the-meter, bloom

The Plant Is Part of the Campus Now

Google's 702 MW Wyoming fuel-cell deal and NTT's 900 MW Bloom agreement put on-site generation on the same procurement path as chillers and switchgear. The IT load is still unpublished.

Read →
7 mincapital, credit, terawulf, coreweave

Hyperscaler Credit Is the New Design Spec

Google is backstopping debt on TeraWulf's 480 MW Kentucky campus leased to Anthropic. The Bank of England is asking about loans to empty shells. Cost of capital just became a site attribute.

Read →