INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST
Markets / West Texas
C&W 2026 Americas · Tertiary #1 · updated 2026-11-05

West Texas (Abilene, Shackelford, Permian)

This is the largest delivered AI capacity in the US, but all of the incremental growth runs through ERCOT's audit and TCEQ air permits. Self-powered campuses are the most exposed to a new governor's air-permit lever.

mixedGrid: ERCOT (Oncor, AEP Texas, co-ops); behind-the-meter gas

C&W: 2.9 GW under construction, more than all of EMEA [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05); F&L Asia: Global data centre market enters managed growth phase (C&W 2026 figures) (2026-05)]

Power and the queue

Notable projects owners where public

Regulatory posture incentives, moratoria, zoning, water, large-load rules

Pending legislation and actions 1 items

DateJurisdictionItemStatusImpactSource
2026-11-04Texas
state
Governor-elect pledge: statutory moratoriumuncertain
Gina Hinojosa (elected Nov 3) campaigned on an immediate moratorium lasting until the Legislature passes protections. BMI says the pause could plausibly extend into late 2027.
proposedhigh[DCD: Anti-data center candidates claim victory across the US in 2026 midterm elections (2026-11-04)]

In force / enacted 3 items

DateJurisdictionItemStatusImpactSource
2026-09-21Texas
state
Governor directive: TCEQ to halt data center permits
TCEQ is to issue no permits for infrastructure directly supporting data centers until ERCOT's audit is complete. TCEQ reported compliance on Oct 19, and a watchdog says some permits still advanced.
in forcehigh[Office of the Texas Governor: Governor Abbott directs TCEQ to halt data center permits (2026-09-21)]
2026-08-03Texas
state
Governor directive: comprehensive data center audit (ERCOT Batch Zero)
PUCT/ERCOT must verify and audit data centers in the interconnection queue. ERCOT is not approving energization of new data center and crypto loads of 75 MW or more until the audit is complete. Verification and community-impact reports are due Dec 10, 2026.
in forcehigh[Office of the Texas Governor: Governor Abbott directs comprehensive data center audit (2026-08-03)]
2025-06-20Texas
state
SB 6 (89R, 2025)
Requires PUCT/ERCOT large-load planning and interconnection standards; applies to large loads at a default 75 MW single-site threshold; addresses interconnection studies, cost allocation, co-location, and emergency curtailment
enactedhigh[SB 6 (89R, 2025) primary source (2025-06-20)]

Open the full TX tracker →

Pricing & supply snapshot directional

MW Desk estimate / directional range, Q4 2026

Not yet benchmarked. We have not published a directional colocation pricing or supply band for this market yet.

Ranges, when published, are indicative only and age quickly. Confirm with brokers and operators before acting.

TJ field notes

Coming soon: TJ's on-the-ground notes on this market. Expect what the queue really looks like, which sites can actually get power, and what the brokers aren't saying.

Slot reserved for TJ's detailed market report.