THE MW DESK / BLOG
In Texas, 'Firm' Now Means Capped
About 107 GW of the 125 GW ERCOT is studying in Batch Zero took the plain firm path. That path comes with a ceiling nobody has published yet. Until the LPC numbers land, a Texas megawatt is a request, not an asset.
On Tuesday morning, bitcoin miner Canaan ($CAN) told investors its 1 GW Duval County, Texas project had received a conditional “Studied Load: Firm” classification under ERCOT’s Batch Zero process, a milestone the company itself called “subject to further studies and approvals” (Canaan Q3 release).
Expect to see that phrase in a lot of Texas decks. It sounds like the strongest word in the grid vocabulary. Under Batch Zero rules it means something narrower: you are in the study, and you will get a ceiling.
The bigger story is how many projects ended up in that same box.
The sort ERCOT just ran
Batch Zero replaces one-at-a-time studies for loads of 75 MW or more with a single system-wide study that allocates the transmission capacity ERCOT can find. The Public Utility Commission approved the rules on June 18, 2026. ERCOT was tracking more than 438,000 MW of large-load requests at the time, nearly 89% of them data centers (Sheppard).
ERCOT’s September board update gave the first cut (ERCOT Board Item 14):
- Base load: 204 projects, 66.4 GW. These are energized or far enough along to be modeled as background load. No new allocation.
- Studied load: 158 projects, shown as 125.4 GW on ERCOT’s chart (127.9 GW in the summary text). These get studied and allocated.
- Excluded: 373 projects, 302.2 GW. They wait for a future batch.
Studied load then splits three ways. WLPUN projects bring their own generation behind one interconnection point. PCLR projects register as controllable load and follow ERCOT dispatch. Firm is ERCOT’s label for everything that chose neither.
Read the 2032 column of ERCOT’s stacked chart and the split is lopsided. By our read, about 107.4 GW of studied load is Firm, about 9.5 GW is WLPUN and about 8.5 GW is PCLR. The WLPUN figure matches the 9,478 MW of load on ERCOT’s own WLPUN detail slide, and the three add up to the 125.4 GW total. Roughly 86% of the megawatts ERCOT is studying took the plain firm path.
What firm actually buys
Each studied load gets two numbers out of the study. The Maximum Power Consumption (MPC) is the full peak the developer asked for. The Low Power Consumption (LPC) is the most it can draw from the grid on a firm basis, with no dispatch or curtailment obligation (Sheppard).
A studied load that did not elect PCLR or WLPUN by July 10, 2026 is capped at its LPC. Willkie Farr & Gallagher put it bluntly: the load can interconnect and operate, “but only up to that LPC cap,” and for many large loads that allocation “will be significantly less than their desired full operating capacity” (Willkie).
So the firm label carries no promise of the headline number. It promises a ceiling, and nobody has seen the ceiling yet. The election window closed in July, so a firm project can’t decide now that it would rather be flexible.
That is the non-obvious part. Most of the market spent the past year assuming the scarce thing in Texas was a spot in the queue. Batch Zero says the scarce thing is the gap between LPC and MPC, and about 86% of studied megawatts chose not to buy a way across it.
The two ways across, and what they cost
Flexibility. A PCLR can run above its LPC up to its MPC, but it must follow ERCOT’s dispatch instructions at all times, including instructions to curtail. ERCOT does not guarantee delivery at MPC in real time, and the obligations transfer automatically to a buyer or lender in any M&A or project finance deal (Sheppard). That is a hard sell to a tenant that bought uptime. We covered the same trade in California and PJM in Flexibility Is the New Interconnection. Texas has now priced it, and only about 8.5 GW took it.
Bring your own power. ERCOT’s WLPUN slide shows 11 projects with 9,478 MW of load paired with 15,444 MW of generation. Of that generation, 12,824 MW is gas, 1,654 MW is solar, 637 MW is wind and 330 MW is battery. Nine of the 11 have more generation than load (ERCOT). And the structure is sticky: a WLPUN can only be dissolved after ERCOT confirms the needed transmission is energized (Sheppard). The bring-your-own-power path in Texas runs on almost 13 GW of gas plants, which runs straight into the turbine queue we wrote about in The Backlog Is the Schedule.
The capital is real even when the megawatts aren’t
Studied loads post financial security for the upgrades needed to serve them. Where costs can’t be determined, the default is $50,000 per MW. Withdraw, or miss phased energization milestones by six months, and 80% of the remaining security goes to the transmission provider’s rate base while 20% comes back. Direct interconnection costs are paid in cash and are non-refundable (Sheppard).
At that default rate, a 1 GW request works out to $50 million of security posted against an MW allocation that won’t be known until the study is done. The money is put down for the full request, while the right to draw power is capped at an LPC nobody has seen.
Policy just moved the clock again
The original schedule had final classifications on August 7, 2026 and study results on April 9, 2027. Then Gov. Abbott’s August 3 directive triggered an eligibility audit. ERCOT now says final inclusion and exclusion decisions come in December, it will file the verification report and a community impact review by December 10, 2026, and the effect on the study timeline is “TBD” (ERCOT).
On top of that, Governor-elect Gina Hinojosa, who takes office January 19, has pledged a moratorium on all data center approvals until the Legislature passes new protections. Her stated priorities include union labor requirements, water protections and an end to NDAs (Texas Tribune). Aurora Energy Research’s Olivier Beaufils told the Houston Chronicle the pause could run to June or July, and a law passed next session wouldn’t take effect until September (Houston Chronicle). We laid out the extended-pause case in Texas Just Extended the Pause.
Put those together and a firm Texas project may be waiting on three separate decisions: whether it survives the December audit, what its LPC turns out to be, and what the 2027 Legislature adds on labor, water and cost allocation.
Where the megawatts are
ERCOT’s top counties for base plus studied load are Cameron (12,235 MW), Dallas (7,637 MW), Jones (7,000 MW), Harris (6,899 MW) and Childress (6,750 MW) (ERCOT). Multi-gigawatt requests are stacked on single counties, and that is where the gap between the land price, set on the headline MW, and the power right, set by the LPC, will be widest.
The angle by seat
Builders and developers. Your LPC is the product. Plan the first phase around a conservative firm number and treat everything above it as upside that has to be earned with flexibility, on-site power or a later batch. If you have union labor exposure in your cost model, put it in now rather than after the session.
Buyers and tenants. When a Texas site is pitched as “1 GW, ERCOT Batch Zero,” ask three questions: base or studied, which lane, and what LPC by year. A firm project with no LPC yet is a land position with a study ticket. It is not delivered capacity. That is the same lesson as Contracted Megawatts Are the Ones That Count, applied to the grid side.
Investors. Discount Texas headline megawatts by lane. Base load is closest to real. WLPUN is real if the gas plant gets built. PCLR is real but curtailable, and the obligations follow the asset into any sale. Firm studied load is a number with a ceiling still to be set. Not investment advice.
What to watch
- By December 10, 2026: ERCOT files the Batch Zero eligibility verification report and the community impact review with the PUCT, and final inclusion and exclusion decisions follow in December.
- The study date: whether ERCOT holds anything close to the original April 9, 2027 date for LPC allocations, and the 30-day interconnection agreement window that follows.
- January 19, 2027: Hinojosa takes office. Watch whether a moratorium order touches Batch Zero allocations or only new approvals.
- June 1, 2027: the Batch Zero transmission plan goes to ERCOT’s Regional Planning Group, with a final plan expected in fall 2027. That is the document that says when the gap between LPC and MPC starts to close.
- The first published LPC: whoever discloses one first, Canaan included, gives the market its first real look at how much a “firm” Texas gigawatt is actually worth.
Sources
- ERCOT, Board Item 14: Batch Zero Update, September 14–15, 2026
- Sheppard, PUCT Approves “Batch Zero” Framework, June 23, 2026
- Willkie Farr & Gallagher, ERCOT Approves Implementing New “Batch Zero Process” for Large Load Interconnections, June 2026
- Canaan Inc., Unaudited Third Quarter 2026 Financial Results, November 10, 2026
- Texas Tribune, Under Hinojosa, Texas data center approvals could stay paused, November 4, 2026
- Houston Chronicle, Texas data centers could see delays, cancellations as statewide Dems take office, November 2026
The 2032 split by lane is our reading of ERCOT’s stacked chart, cross-checked against its WLPUN detail slide. This post is for information only and is not legal, engineering or investment advice.