The NDA Is Dying. The Secret Moved to the Land Deal.
Microsoft, Amazon and now OpenAI have sworn off NDAs with public officials. Microsoft kept them for land buys. Disclosure is turning into the entitlement package, and the exposed party is the developer standing between the hyperscaler and the county.
Three of the biggest buyers of data center capacity have now said the same thing: no more NDAs with public officials. Microsoft said it in March. Amazon said it in October. OpenAI said it on November 5, the day after voters in Ohio, Texas and elsewhere made data centers a ballot issue.
The easy read is that secrecy is over. The fine print tells a different story. The secret did not die. It moved upstream, to the land deal, and the window between controlling a site and telling the public about it is now where the value gets made or lost.
Read what was kept, not what was dropped
Microsoft’s own explainer is the clearest map. Its development process “proceeds in stages, just like any commercial real estate development,” it wrote. “The first stage is to purchase land,” followed by design, site grading and vertical construction. It is terminating active NDAs with local governments and will still seek to shield design and security details from records requests where the law allows (Microsoft).
Rima Alaily, who leads Microsoft’s infrastructure legal affairs, was more direct: the company will keep using NDAs in private land acquisitions (WPR). She added: “Our neighbors deserve to know when we are coming to their community.”
Both statements can hold at once. Neighbors learn when the hyperscaler comes to the county. They do not learn before the hyperscaler controls the dirt.
OpenAI’s National Community Compact follows the same pattern. It bars NDAs with public officials and keeps “narrow protections covering legitimate security information, trade secrets, or proprietary or competitively sensitive information.” It also applies only to future campuses OpenAI “owns and operates” (OpenAI; The Verge).
Policy is also making room for a pre-disclosure window. Florida’s SB 484, the state’s new large-load cost law, lets cities and counties sign NDAs with tech companies for up to 12 months (WUSF). Secrecy has gone from a default to a time-limited allowance.
The exposed party is the one in the middle
The hyperscalers are often not the ones who signed these agreements. WIRED reported that end tenants like Amazon “are often not the companies directly interfacing with government officials.” In Wharton County, Texas, a top official signed an NDA with a contractor, VisionFirst Advisors, not with Amazon. Amazon did not answer WIRED’s question about whether its NDA promise extends to contractors (WIRED). DCD noted that Amazon’s post did not address shell companies or project code names (DCD).
That is the gap. The brand-name tenant now has a public, written commitment to transparency. The site selector, the land assembler and the third-party developer building to suit do not. When a county finds out a year later that the code-named project was for a company that publicly swore off secrecy, the anger lands on everyone in the chain, and the tenant has a written policy it can point to when it walks.
Political pressure is closing in on the whole chain. Pennsylvania, Massachusetts and Delaware governors have cracked down on data center NDAs by executive order. New York, New Jersey, Indiana and Ohio have weighed bans. A bipartisan House bill, the No Secrets for Data Centers Act, was introduced, and one of its sponsors, Rep. Jamie Raskin, sent letters to Amazon, Google, Meta and Oracle asking about their use of NDAs (WIRED). Minnesota Representative-elect Matt Little has pushed for a national ban on data center construction and NDAs (USA TODAY).
Disclosure is becoming the underwriting package
Read OpenAI’s compact as a term sheet rather than a press release. Before major spending, it promises financial assurances so other utility customers are protected if a project is delayed, cut back or canceled. It promises a water plan per campus, site-level water and electricity reporting, construction plans and independent noise studies published before operations, published job forecasts, and annual reports on hiring and apprenticeships (OpenAI).
Each item touches a different part of the stack.
Power. Collateral posted before spending turns a political promise into a balance-sheet item. The same logic is spreading through utilities: Big Rivers Electric’s CEO told Kentucky lawmakers on November 5 that “any and all costs” should fall on the developer, “from the very upfront request for studies” (WDRB). We covered tariff design in Who Pays for the Large Load?. The new part is timing. The money now shows up before major spending begins, not after the meters are set.
Flexibility. OpenAI’s blueprint cites its Georgia Power agreement for the planned Effingham County campus, which lets the utility cut deliveries to OpenAI by up to 1,000 MW during high demand (OpenAI). Once curtailment terms like that are public, every county will ask the next applicant why its deal has none. More on that trade in Flexibility Is the New Interconnection.
Supply chain and labor. The blueprint asks developers to share purchasing plans early enough for local suppliers to bid. It also wants trades unions and community colleges to use hiring forecasts to train residents, “from electrical work during construction to maintaining power and cooling systems” (OpenAI). Published headcount forecasts will make labor shortfalls visible campus by campus. That is a risk for schedules and a lever for the electrician shortage.
Incentives. The blueprint wants tax-incentive terms made public, with measurable commitments and a way to recover benefits if a developer falls short (OpenAI). Clawbacks written by the tenant’s own policy shop will be hard to bargain away at the county level.
Put those together and the entitlement file starts to look like a lender’s diligence binder, posted publicly. Projects that can fill it in early will clear. Projects whose economics depended on nobody knowing the water draw or the curtailment terms will not.
Why the land window just got more valuable
If disclosure at the county is now the norm, the period before disclosure is the only private part of the process left. That raises the value of three things.
First, land already controlled before a project goes public, ideally with zoning that does not need a fresh hearing. Second, existing campuses with room to expand. Meta’s president told the Wall Street Journal the company will have an easier time expanding existing data centers than building new ones after the midterms (USA TODAY). Third, developers whose disclosure record already holds up. Those are the ones a tenant bound by a public compact can safely put its name next to.
The losers are business models built on the code name: assemble quietly, entitle quietly, reveal the tenant after the vote. That sequence now carries reputational risk for the tenant and legal risk wherever states finish writing the bans. Over 440 data center moratoriums are active in the U.S., per a tracker cited by USA TODAY (USA TODAY). A secrecy fight that surfaces mid-process is now one of the fastest ways to turn a site into one of them.
Why it matters for builders, buyers and investors
Builders and developers: Write your own compact before a tenant hands you theirs. Model the cost of collateral posted before spend, published water and noise studies, and hiring reports into the pro forma. If your land strategy relies on a contractor-level NDA, assume it becomes public and plan the reveal.
Buyers and tenants: Your public pledge travels with your name. Ask developers and site selectors to confirm, in writing, what they signed with local officials on your behalf. A powered shell with a clean disclosure history is a different product from one with a buried agreement, even at the same MW and the same rent.
Investors: Underwrite disclosure as a schedule item. Pre-spend financial assurances raise the equity needed before a shovel moves, which favors sponsors with real balance sheets, the same split we flagged in Existing Capacity Just Got More Valuable. Platform valuations that assume a quiet entitlement path in states that just voted for transparency deserve a haircut. $MSFT and $AMZN have both made public NDA commitments; watch whether their developer partners match them.
What to watch
- Whether Google, Meta and Oracle publish NDA policies, and whether any of the three hyperscaler pledges is extended to contractors, site selectors and leased capacity.
- The No Secrets for Data Centers Act in the new Congress, and the state bans in New York, New Jersey, Indiana and Ohio.
- How Florida counties use the 12-month NDA window, and Duke Energy Florida’s refiled large-load tariff (WUSF).
- The first OpenAI local compact with site-level water, power and hiring numbers, and whether other tenants start requiring the same from landlords.
- Our legislation tracker and development sites desk for where land with clean entitlement paths is still available.
Not investment advice.
Sources
- https://openai.com/index/setting-new-standard-responsible-ai-infrastructure ↗
- https://www.theverge.com/ai-artificial-intelligence/1028454/openai-data-center-nda ↗
- https://local.microsoft.com/blog/putting-communities-first-our-decision-to-end-ndas-with-local-governments/ ↗
- https://www.wpr.org/news/microsoft-to-stop-using-ndas-with-local-governments-for-data-center-development ↗
- https://www.wired.com/story/amazon-says-it-is-going-to-stop-using-ndas-for-data-centers/ ↗
- https://www.datacenterdynamics.com/en/news/aws-drops-non-disclosure-agreements-for-data-center-projects/ ↗
- https://www.wusf.org/politics-issues/2026-11-04/regulators-reject-dukes-data-center-rate-structure ↗
- https://www.usatoday.com/story/money/2026/11/06/data-centers-midterm-election-regulation-congress-state/92647855007/ ↗
- https://www.wdrbwave.com/2026/11/07/kentucky-utility-leaders-say-data-center-developers-should-cover-project-costs/ ↗