The Other Side of the Footnote: What the Builders Signed Up For
Hyperscaler lease footnotes show demand. The builders' filings show who carries the risk: cost overruns, power delays in Texas, guarantees on GPU orders, borrowing conditions tied to market value, and interest costs that have jumped.
Not financial advice. For informational purposes only. Not investment advice. Analysis only. No price forecasts and no trading recommendations.
Summary
Our companion note tracked about $851 billion of leases that hyperscalers have signed but not yet started. This note reads the filings of the companies building that capacity. The pattern is consistent: the neoclouds and converted miners carry the construction, power and financing risk until rent starts, and several have taken on terms that tighten if anything slips.
What the filings say (risk and debt first)
- Cost overruns sit with the landlord. Cipher $CIFR "will bear the first $359.3 million of costs in excess of the initial budgeted amount under the Barber Lake Lease" [S1].
- Power timing in Texas (ERCOT). Cipher also disclosed that "ERCOT has temporarily paused certain energization approvals for large data center loads pending completion of that process", and that ERCOT "currently expects to issue the related reports by December 10, 2026" [S2]. It warns the reviews "could delay or prevent the interconnection or energization of our data centers" [S2].
- Borrowing tied to market value. Core Scientific $CORZ can draw its revolver only if it has "a minimum market capitalization of not less than $3,000.0 million as of market close on the trading day immediately preceding each borrowing date" [S3]. Liquidity backup that depends on the share price is weakest exactly when it is needed.
- Guarantees on GPU orders. IREN $IREN subsidiaries agreed to purchase GPUs from Dell for "an aggregate purchase price of approximately $6.7 billion", with deliveries starting in the second half of calendar 2027, and "the Company has agreed to unconditionally guarantee the obligations of the Purchasers" [S4]. IREN's commitments rose to "$18,947 million, as compared to $13,810 million as of June 30, 2026" [S4], an increase of about $5.1 billion in one quarter.
- Interest costs. TeraWulf $WULF reported Q1 2026 interest expense of 67,071 versus 4,049 a year earlier (thousands) [S5].
- Power before customers. CoreWeave $CRWV says it expects to commit "long-term power supply contracts, in advance of securing customer contracts for those data centers" [S6].
Connecting the dots
- Credit support is the real collateral. TeraWulf says its Fluidstack leases "benefit from substantial credit support provided by Google" [S7]. Alphabet $GOOGL lists $130.5 billion of leases not yet commenced [S8]. Lenders to these builders are underwriting a large technology company's backstop, not the builder's own cash flow.
- The hyperscaler gets flexibility, the builder gets the fixed costs. Microsoft's lease footnote now says some arrangements are "subject to certain contractual conditions being met" [S9]. If start dates move, the builder still owes interest on construction debt, still owns overrun exposure, and may still have prepaid for power.
- Texas is the pressure point to watch now. ERCOT's pause on certain large-load energization approvals [S2] lands on the same projects whose rent depends on energization. A December 10, 2026 report date gives a concrete marker.
- Rates. The 10-year Treasury was 5.10% on November 12, 2026, versus 4.08% a year earlier [S10]. Every month of delay costs more than it did a year ago.
Buyer and investor implication
For credit and lease investors, the builder layer is where the downside is concentrated: fixed overrun shares, guarantees, market-value borrowing conditions and power timing. For tenants and colocation buyers, a delay at an energization queue can push delivery dates even when the lease is signed. Builders with energized power and backstopped tenants are in a different risk class from those still waiting on interconnection.
Scenario outcomes
- Base: ERCOT completes its review and energization resumes on most projects with modest delays. Builders absorb some overruns, and rent commencement shifts by a quarter or two. Backstopped leases hold.
- Bull: approvals resume quickly and tenants take capacity early. Builders with power in hand refinance construction debt at better terms once rent starts.
- Bear: energization delays stretch, overruns hit the capped amounts, and share prices fall far enough to restrict market-value-based borrowing. Builders with guaranteed hardware orders and high interest costs face the tightest liquidity. Hyperscalers keep their options under conditional leases.
What to watch
- ERCOT's large-load reports, expected by December 10, 2026 [S2], and any PUCT action that follows.
- Rent commencement dates in builder 10-Qs and 10-Ks, and any amendments to lease start dates.
- Changes to credit support language and to revolver conditions.
- Whether hyperscaler uncommenced lease totals keep rising while builder interest costs climb.
Not financial advice. For informational purposes only. Not investment advice.
Sources
- [S1] Cipher 10-Q, quarter ended Sep 30, 2026 (filed 2026-11-02): sec.gov ↗ ; also 8-K filed 2026-09-25: sec.gov ↗
- [S2] Cipher 10-Q, quarter ended Sep 30, 2026, regulatory risk discussion: sec.gov ↗
- [S3] Core Scientific 8-K filed 2026-08-27 (credit agreement): sec.gov ↗
- [S4] IREN 10-Q, quarter ended Sep 30, 2026 (filed 2026-11-05): sec.gov ↗
- [S5] TeraWulf 10-Q, quarter ended Mar 31, 2026 (filed 2026-05-08): sec.gov ↗
- [S6] CoreWeave 10-Q, quarter ended Sep 30, 2026 (filed 2026-11-12): sec.gov ↗
- [S7] TeraWulf 10-Q, quarter ended Sep 30, 2026 (filed 2026-11-06): sec.gov ↗
- [S8] Alphabet 10-Q, quarter ended Sep 30, 2026 (filed 2026-10-29): sec.gov ↗
- [S9] Microsoft 10-Q, quarter ended Sep 30, 2026 (filed 2026-10-28): sec.gov ↗
- [S10] FRED DGS10: fred.stlouisfed.org ↗
Math
- IREN commitments: 18,947 - 13,810 = 5,137 million in one quarter.
- TeraWulf interest expense: 67,071 / 4,049 = 16.6x year over year (Q1 2026 vs Q1 2025, thousands).