Markets / Memphis
C&W 2026 grid-stability top 10 · Grid stability #8 · updated 2026-11-05
Memphis / North Mississippi
The largest single AI cluster build, now with a federal court constraint on its on-site power model.
mixedGrid: MLGW / TVA; Entergy Mississippi; on-site turbines
Not in C&W's Americas top 30, but listed #8 for grid stability [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05)]
Power and the queue
- SpaceXAI's Southaven turbines: Mississippi permitted 41 permanent turbines (~1.2 GW). A federal judge ruled on Nov 2, 2026 that the turbines need air permits, and temporary units are under an agreed order for removal. [Mississippi Today: Federal judge rules Southaven data center gas turbines must have air pe (2026-11-02); Commercial Appeal: SpaceXAI, Southaven enter agreed order to remove temporary turbines (2026-07-30)]
Notable projects owners where public
- SpaceXAI (xAI) Colossus 2, Tulane Road, Memphis: an estimated ~946 MW IT capacity (Epoch estimate), expanding into two more Mississippi campuses.uncertain [Epoch AI: Largest AI data centers ranked by power capacity, 2026 (2026-11-05); DCD: SpaceXAI launching two additional data center campuses in Mississippi to expand Colos (2026)]
Regulatory posture incentives, moratoria, zoning, water, large-load rules
- Behind-the-meter gas faces Clean Air Act litigation, a template for challenges elsewhere. [Mississippi Today: Federal judge rules Southaven data center gas turbines must have air pe (2026-11-02)]
Pending legislation and actions 1 items
| Date | Jurisdiction | Item | Status | Impact | Source |
|---|---|---|---|---|---|
| undated | Memphis city | Proposed ordinance declaring a temporary moratorium on acceptance, processing, approval, and issuance of zoning, land use, building, and infrastructure permits for data center developments within the uncertain Duration: 12 months from effective date, or until comprehensive data center zoning is adopted or the ordinance is repealed, whichever is earlier; extendable | pending | medium | [https://wreg.com/wp-content/uploads/sites/18/2026/08/Data-Center-Temporary-Moratorium-Ordi] |
In force / enacted 4 items
| Date | Jurisdiction | Item | Status | Impact | Source |
|---|---|---|---|---|---|
| 2026-10-01 | TVA utility | Data center rate and capacity-commitment charge The board created a separate data center rate, effective Oct 1, 2026. | in force | high | [Nashville Post: TVA votes to increase rate payment for data centers (2026-08)] |
| 2026-05-18 | Tennessee state | HB1847 / SB2128 Applies to data centers at or above 50 MW. Requires data center owners to pay infrastructure costs needed to support utility service and bars ratepayer cost-shifting unless infrastructure also benefits other ratepayers. Reporting states amended bill also allow | enacted | high | [TN General Assembly Bill Status - HB1847 (114th GA)] |
| 2026-04-08 | Mississippi state | SB3410 (2026) Authorizes Brandon and the West Rankin Utility Authority to enter agreements with data center or related technology facility developers/operators for water and wastewater infrastructure, reclaimed water delivery, wastewater treatment, capacity guarantees, assi | enacted | high | [Mississippi Legislature - Senate Bill 3410 (2026) Status History] |
| 2026-04-08 | Mississippi state | HB1393 (2026) Creates the Mississippi Energy Infrastructure Fund. The definition of "project" includes data centers, making data-center-serving energy infrastructure potentially eligible for grants, loans, or other assistance through MDA, while excluding electric utilities | enacted | medium | [Mississippi Legislature - House Bill 1393 (2026) Status History] |
Pricing & supply snapshot directional
MW Desk estimate / directional range, Q4 2026
Not yet benchmarked. We have not published a directional colocation pricing or supply band for this market yet.
Ranges, when published, are indicative only and age quickly. Confirm with brokers and operators before acting.