INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST
Markets / Kansas City
C&W 2026 Americas · Tertiary #6 · updated 2026-11-05

Kansas City

Evergy is contracting real hyperscale load under a strict tariff, while rural Kansas voters are drawing hard lines.

mixedGrid: Evergy (SPP)

[Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05)]

Power and the queue

Notable projects owners where public

No verified public item yet. This is a gap we are working on.

Regulatory posture incentives, moratoria, zoning, water, large-load rules

Pending legislation and actions 1 items

DateJurisdictionItemStatusImpactSource
2026-11-03Ottawa (Franklin Co.)
city
Nov 3, 2026 ballot measureuncertain
Voters banned data centers over 25 MW. A court has not decided whether it is enforceable.
pendingmedium[DCD: Local data center moratoria, limits, and restrictions voted in across the US (2026-11-04)]

In force / enacted 7 items

DateJurisdictionItemStatusImpactSource
2026-08-03Oak Grove
city
Board of Aldermen resolution (agenda item, Aug. 3, 2026 meeting)
City to consider regulations over the course of the year Duration: One year
in forcehigh[Oak Grove Board of Aldermen approve administrative delay on data center development]
2026-07-14Lawrence
city
Lawrence City Commission action, adopted unanimously (5-0) on 2026-07-14, imposing a 24-month moratorium on data center uses within city limits alongside initiation of two Land Development Code text a
24-month freeze on data center uses within Lawrence city limits while planning staff draft a special-use-permit requirement and study issues (water, energy/utility costs, noise, light, setbacks) for a new data center ordinance; includes a narrow property-owner
in forcehigh[https://www2.ljworld.com/news/city-government/2026/jul/14/lawrence-city-commission-starts-]
2026-07-06City of Independence
city
Resolution No. 7238 (City Council agenda item 26-741), 'A resolution declaring a 180-day moratorium on the processing of applications related to and issuance of city permits or licenses related to the
City Council voted 7-0 for a 180-day moratorium on accepting, processing, or issuing permits for new data centers and battery energy storage systems Duration: 180 days
in forcehigh[City Council Regular Meeting Minutes, July 6, 2026 (2026-07-06)]
2026-06-22Jackson County
county
Ordinance 6074, introduced 2026-04-06 by Legislator Sean E. Smith (120-day version); a competing 365-day version (Ordinance 6087, sponsored by Legislative Chair Manny Abarca) was also considered in co
If adopted, the county would use the pause to draft long-term code provisions and enhanced public notice requirements. Duration: 180 days, amended up from the original 120-day Ordinance 6074 proposal introduced 2026-04-06 by Legislator Sean E. Smith. The Legis
in forcehigh[Jackson County legislature passes 180-day moratorium on data center applications (2026-06-22)]
2025-04-24Kansas
state
SB 98 (2025)
Created qualified data center sales tax exemptions for construction/remodeling, equipment, eligible costs, and certain labor for firms committing at least $250 million and meeting jobs and related requirements.
enactedhigh[Kansas Legislature - SB 98 (2025-26) history]
2025-04-09Missouri
state
SB 4 (2025)
Utility law requiring large-load tariff filings. Missouri PSC later approved Ameren Missouri's large-load plan for customers needing 75 MW or more of monthly peak demand, including data centers, with customer-protection terms.
enactedhigh[SB 4 - Bill Information - Missouri Senate]
2026-08-16Evergy (KS/MO)
utility
Large Load Power Service tariff
For new loads above 75 MW: 12-year minimum term, minimum bill at 80% of contracted capacity, collateral.
in forcemedium[Topeka Capital-Journal: Data center demand fuels Evergy plan for more power plants in Kans (2026-08-16)]

Open the full MO tracker →

Pricing & supply snapshot directional

MW Desk estimate / directional range, Q4 2026

Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.

  • Retail colo (roughly 0–250 kW): $145–340/kW-mo
  • Wholesale (roughly 250 kW–4 MW): $105–205/kW-mo
  • Large / hyperscale blocks (roughly 4 MW+): $100–200/kW-mo
  • Vacancy band: low-to-mid teens (soft relative to primary markets)
  • Commissioned inventory (directional): ~90–160 MW
  • Available power (directional): ~0–35 MW
  • Under construction: ~0–30 MW
  • Planned pipeline: ~115–185 MW
  • Absorption: flat / little net absorption in the latest quarter
  • Power / timing: More near-term colo availability than primary AI markets; still confirm substation and transmission timing for large loads.

Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.

TJ field notes

Coming soon: TJ's on-the-ground notes on this market. Expect what the queue really looks like, which sites can actually get power, and what the brokers aren't saying.

Slot reserved for TJ's detailed market report.