INDEPENDENT DATA CENTER INTELLIGENCERESEARCH SNAPSHOT · NOV 05, 2026 · PST
Markets / Chicago
C&W 2026 Americas · Primary #5 · updated 2026-11-05

Chicago

There's no state incentive for new deals, a city moratorium is drafted, and ComEd is demanding money up front. The queue shrinking from 39 to 25 GW is healthy, but the economics of new Illinois builds just got worse.

coolingGrid: ComEd (Exelon, PJM)

CBRE H1 2026: 910.6 MW inventory, 2.2% vacancy [Cushman & Wakefield, 2026 Global Data Center Market Comparison (Americas rankings) (2026-05); CBRE press release: demand continues to outpace supply (H1 2026 market table) (2026-08); Data Center Frontier: CBRE record construction fails to ease capacity crunch (2026-08)]

Power and the queue

Notable projects owners where public

No verified public item yet. This is a gap we are working on.

Regulatory posture incentives, moratoria, zoning, water, large-load rules

Pending legislation and actions 12 items

DateJurisdictionItemStatusImpactSource
2026-09-23Chicago
city
Proposed 12-month moratorium ordinance
Would pause new data centers and major expansions. Referred to Rules with no hearing yet.
pendinghigh[City of Chicago: Mayor Johnson and Council members introduce data center moratorium ordina (2026-09-23)]
2026-06-17Illinois
state
SB4004 (Aquifer Protection Act)
Creates Data Center Water Transparency and Aquifer Protection Act; bars data centers from using Mahomet Aquifer water beginning 2027; bars permits for Mahomet withdrawals; requires existing users to transition by 2028; bans local nondisclosure clauses restrict
pendinglow[SB4004 Bill Status - Illinois General Assembly]
2026-05-30Illinois
state
SB4016 (Hyperscale Data Centers / POWER Act)
Comprehensive hyperscale data center regulation: cumulative impact review, public notice, community benefit agreements, NDA restrictions, water-impact permits, quarterly water reporting, water scarcity plans, energy and water reporting to ICC, hyperscale self-
pendinglow[SB4016 Bill Status - Illinois General Assembly]
2026-05-27Illinois
state
HB5513 (Hyperscale Data Centers / POWER Act companion)
House companion to SB4016 with environmental, water, energy, public-benefit, reporting, and solar permitting provisions.
pendinglow[HB5513 Bill Status - Illinois General Assembly]
2026-05-22Illinois
state
SB2181 (Data Center Reporting)
Creates Illinois Data Center Energy and Water Reporting Act; annual energy and water reporting to IPA; IPA ratepayer-impact study; confidentiality, public access, enforcement, and penalties.
pendinglow[SB2181 Bill Status - Illinois General Assembly]
2026-05-22Illinois
state
SB3120 (DCEO-Data Centers)
Conditions data center incentive qualification on water stewardship strategy disclosure and requires DCEO reporting on recipient water stewardship strategies.
pendinglow[SB3120 Bill Status - Illinois General Assembly]
2026-05-22Illinois
state
SB3761 (Data Centers-Various)
Establishes data center self-direct clean energy program, 180-day preconstruction disclosure to ICC, public meeting requirements, water-use disclosures to DNR, penalties up to $10,000 per violation, and utility tariff review.
pendinglow[SB3761 Bill Status - Illinois General Assembly]
2026-05-22Illinois
state
SB3830 (Data Centers-Various)
Similar clean energy self-direct and utility tariff framework; adds water discharge pollutant identification, DNR water-use disclosure, Water Use Act changes, and groundwater emergency provisions.
pendinglow[SB3830 Bill Status - Illinois General Assembly]
2026-01-14Illinois
state
HB4319 (Data Center-Property Rights)
Creates a compensation framework for property owners within 1,000 feet of a data center for value loss, business revenue loss, or adverse impacts such as noise, vibration, traffic, stormwater burden, or lighting; limits concurrent home-rule powers.
pendinglow[HB4319 Bill Status - Illinois General Assembly]
2025-06-02Illinois
state
HB3574 (Procurement-Data Residency)
Requires state data storage contracts to keep data in the United States and creates bid credits for Illinois and opportunity-zone storage, including data center-related provisions.
pendinglow[HB3574 Bill Status - Illinois General Assembly]
2025-06-02Illinois
state
SB2290 (Use/Occ Tx-Quantum Computing)
Expands the state data center definition for incentive purposes to include a quantum research facility.
pendinglow[SB2290 Bill Status - Illinois General Assembly]
2025-04-03Illinois
state
SB0094 (Data Centers-Foreign Ownership)
Confirmed via ILGA synopsis: creates the Data Center Construction by Foreign Adversaries Act; bars a foreign-adversary-controlled company from constructing a data center in Illinois unless ICC, IPA, and DCEO jointly certify load conditions.
pendinglow[SB0094 Bill Status - Illinois General Assembly]

In force / enacted 10 items

DateJurisdictionItemStatusImpactSource
2026-11-03Joliet; Chouteau, Granite City, Nameoki and Venice Twps (Madison Co.)
city
Nov 3, 2026 ballot measureuncertain
Advisory questions: voters said officials should not permit data centers.
enactedhigh[DCD: Local data center moratoria, limits, and restrictions voted in across the US (2026-11-04)]
2026-10-09PJM (13 states + DC)
utility
FERC order ER26-3515: PJM Large Load definition and registry
FERC accepted the definition and registry, effective Oct 12, 2026, and rejected the rest of the filing. The registry is not a public per-request queue.
enactedhigh[FERC order ER26-3515 on PJM Large Load definition and registry (2026-10-09)]
2026-09-16Gary
city
Executive Order signed by Gary Mayor Eddie D. Melton on 2026-09-16, pausing approval of new data center development in the city
Mayor issued a one-year executive-order moratorium on new data center development Duration: One year from the executive order
in forcehigh[https://gary.capitalbnews.org/gary-data-center-moratorium/]
2026-09-08Lake County
county
Lake County Ordinance 26-1018, amending Chapter 151 (Unified Development Ordinance) of the Lake County Code of Ordinances to define and impose a temporary moratorium on data centers in unincorporated
Temporary pause while the County studies infrastructure, environmental, and community impacts and develops a regulatory framework, which officials say could serve as a resource for surrounding communities. Duration: Eight-month moratorium on data centers in un
in forcehigh[https://www.shawlocal.com/lake-county-journal/2026/09/08/lake-county-oks-temporary-morator]
2026-07-20City of West Chicago
city
City of West Chicago Ordinance 26-O-0011
Duration: 180-day moratorium on receipt, processing, and final approval of applications and permits for data centers and battery energy storage systems in every zoning district; protects complete pre-effective-date applications and approved permits, includes l
in forcehigh[City of West Chicago]
2026-06-05Illinois
state
Governor directive: pause Data Center Investment Program
DCEO stopped processing new data center incentive applications and agreements on Jul 1, 2026, with no stated end date. Pre-Jul 1 agreements are honored.
in forcehigh[Gov. Pritzker pauses new data center tax incentives (2026-06-05)]
2026-05-26Merrillville (Lake County)
town
Town Council vote (7-0) imposing a one-year moratorium on data center project approvals; ordinance or resolution number not captured in sources reviewed
Town Council voted 7-0 to impose a one-year moratorium on data center project approvals; the town also held a June 11, 2026 educational meeting. Duration: One year, June 1, 2026 through May 31, 2027
in forcehigh[Town of Merrillville, Indiana (2026-05-26)]
2026-04-21Plainfield
village
Village of Plainfield ordinance establishing a 180-day moratorium on data centers and computing-infrastructure warehouses (specific ordinance number not published in sources reviewed)
Pause to allow staff, elected officials, and consultants to study best practices and develop a new unified development ordinance addressing data centers. Duration: 180-day moratorium on the receipt, processing, approval, and permitting of applications for data
in forcehigh[https://patch.com/illinois/plainfield/data-center-moratorium-imposed-plainfield-after-unan]
2026-09-16ComEd
utility
Large-load deposits and transmission security agreements
Over $1B in financial commitments collected. The queue fell to about 25 GW from about 39 GW, and the ICC is investigating a tariff framework.
in forcemedium[ComEd: secures over $1 billion in financial commitments from large load projects (2026-09-16)]
2026-08-11Chicago
city
Mayoral executive order: enhanced data center review
Creates enhanced regulatory review and a task force, and calls for a Council moratorium.
in forcemedium[City of Chicago: Mayor Johnson signs executive order creating enhanced review for data cen (2026-08-11)]

Open the full IL tracker →

Pricing & supply snapshot directional

MW Desk estimate / directional range, Q4 2026

Asking-rate bands below are MW Desk directional estimates in USD per kW-month. They are rounded ranges, not quoted rates, and they go stale quickly.

  • Retail colo (roughly 0–250 kW): $155–405/kW-mo
  • Wholesale (roughly 250 kW–4 MW): $100–220/kW-mo
  • Large / hyperscale blocks (roughly 4 MW+): $100–220/kW-mo
  • Vacancy band: roughly 2–4% (tight)
  • Commissioned inventory (directional): ~1.5–2.0 GW
  • Available power (directional): ~20–55 MW
  • Under construction: ~25–60 MW
  • Planned pipeline: ~4.7–5.2 GW
  • Absorption: strong positive absorption
  • Power / timing: Near-term wholesale blocks are limited; most near-term MW is spoken for or pre-leased.

Indicative only. Ranges are rounded and adjusted directional estimates, not quoted asking rates or a survey. Confirm with brokers and operators before acting. Source data ages quickly.

TJ field notes

Coming soon: TJ's on-the-ground notes on this market. Expect what the queue really looks like, which sites can actually get power, and what the brokers aren't saying.

Slot reserved for TJ's detailed market report.